標準解讀
《GB/T 18482-2026 可逆式抽水蓄能機組啟動試運行規程》相較于《GB/T 18482-2010 可逆式抽水蓄能機組啟動試運行規程》,在多個方面進行了更新和調整。這些變化主要體現在技術要求的細化、安全措施的加強以及對環境影響的關注上。
首先,在技術要求部分,新版本增加了對于數字化與智能化技術的應用指導,比如明確了遠程監控系統的技術參數及其安裝調試過程中的具體步驟。此外,還對機組性能測試方法進行了詳細規定,包括但不限于效率曲線測定、振動噪聲水平測量等項目,并且引入了更多現代化檢測手段來確保數據準確性。
其次,關于安全措施方面,《GB/T 18482-2026》強調了更加嚴格的安全操作流程及應急預案制定要求。例如,新增了針對極端天氣條件下如何保障設備正常運轉的相關內容;同時,也提高了對工作人員職業健康保護的標準,如增加了個人防護裝備配置建議等。
再者,考慮到環境保護日益受到重視,《GB/T 18482-2026》特別增加了對生態影響評估的要求。這不僅涉及到施工期間可能產生的污染控制措施,還包括長期運營中如何減少對周邊自然環境的影響等方面的規定。
最后,新版標準還對文檔記錄提出了更高的要求,旨在通過完善的數據收集與管理機制促進整個行業的規范化發展。
如需獲取更多詳盡信息,請直接參考下方經官方授權發布的權威標準文檔。
....
查看全部
- 現行
- 正在執行有效
- 2026-04-30 頒布
- 2026-04-30 實施
文檔簡介
ICS27.140
CCSF29
中華人民共和國國家標準
GB/T18482—2026
代替GB/T18482—2010
可逆式抽水蓄能機組啟動試運行規程
Codeforstartupandcommissioningofreversiblepumpedstorageunits
2026?04?30發布2026?04?30實施
國家市場監督管理總局
國家標準化管理委員會發布
GB/T18482—2026
目次
前言··························································································································Ⅲ
1范圍·······················································································································1
2規范性引用文件········································································································1
3術語和定義··············································································································1
4總體要求·················································································································2
5啟動前準備··············································································································2
5.1一般要求···········································································································2
5.2文件資料準備·····································································································2
5.3系統和設備檢查··································································································3
5.4啟動條件確認·····································································································7
6啟動試驗·················································································································7
6.1一般要求···········································································································7
6.2抽水調相啟動試驗·······························································································8
6.3抽水調相工況試驗······························································································10
6.4抽水工況試驗····································································································10
6.5發電啟動試驗····································································································11
6.6發電工況試驗····································································································16
6.7發電調相工況試驗······························································································18
6.8其他工況轉換試驗······························································································19
6.9涉網試驗··········································································································19
6.10黑啟動試驗·····································································································20
6.11試驗驗收········································································································20
7試運行··················································································································20
8交接·····················································································································21
附錄A(資料性)可逆式抽水蓄能機組啟動試運行組織機構工作職責和內容····························22
附錄B(資料性)啟動試運行大綱編制內容······································································24
B.1工程概述·········································································································24
B.2編制依據·········································································································24
B.3啟動試運行組織機構及職責·················································································24
B.4機組啟動范圍···································································································24
B.5機組啟動試運行前具備的條件··············································································24
B.6啟動試驗項目及措施··························································································24
B.7啟動試運行安全保證措施····················································································24
Ⅰ
GB/T18482—2026
B.8啟動試運行試驗質量管理····················································································24
B.9啟動試運行試驗計劃安排····················································································24
B.10附件··············································································································24
附錄C(規范性)輸水系統和機組流道充水······································································25
C.1尾水系統充水···································································································25
C.2蝸殼與尾水管充水·····························································································25
C.3引水系統充水···································································································25
附錄D(規范性)電站受電···························································································27
D.1電站受電前應具備的條件····················································································27
D.2電站受電試驗的一般程序及要求···········································································27
附錄E(資料性)機組首次啟動方式選擇·········································································29
附錄F(規范性)機組動平衡試驗··················································································30
F.1一般要求·········································································································30
F.2試驗步驟·········································································································30
附錄G(資料性)可逆式抽水蓄能機組啟動試運行應交接驗收的資料目錄·······························31
G.1管理性文件······································································································31
G.2資料性文件······································································································31
Ⅱ
GB/T18482—2026
前言
本文件按照GB/T1.1—2020《標準化工作導則第1部分:標準化文件的結構和起草規則》的規
定起草。
本文件代替GB/T18482—2010《可逆式抽水蓄能機組啟動試運行規程》,與GB/T18482—2010
相比,除結構調整和編輯性改動外,主要技術變化如下:
——更改了標準的適用范圍,將可逆式抽水蓄能機組更改為可逆式抽水蓄能定速機組(見第1章,
2010年版的第1章);
——更改了術語和定義(見第3章,2010年版的第3章);
——將“總則”更改為“總體要求”,明確了啟動試運行的工作程序(見第4章,2010年版的
第4章);
——將“設備分部調試及啟動試運行前的檢查”更改為“啟動前準備”,刪除了設備分部調試的內
容,增加了啟動前應完成的工作和文件資料準備(見5.1、5.2,2010年版的6.1);
——增加了檢查調速系統壓力油罐事故低油壓和事故低油位、導葉接力器全開行程和關閉時間及
機械過速動作和失電關閉導葉功能等要求(見5.3.3);
——增加了檢查主進水閥壓力油罐事故低油壓和事故低油位、水壓控制裝置、工作密封與活門閉
鎖功能及機械過速動作和失電關閉主進水閥功能等的要求(見5.3.4);
——增加了檢查靜態充氣壓水和回水排氣試驗的要求(見5.3.5.8);
——增加了檢查高壓油頂起裝置交、直流泵切換功能及機械制動投入和退出故障模擬的要求
(見5.3.6);
——增加了檢查靜止變頻器(SFC)小電流試驗要求(見5.3.8);
——增加了檢查電氣一次、電氣二次系統設備與其他機組隔離措施的要求(見5.3.9、5.3.10);
——增加了檢查發電電動機氣體滅火系統的要求(見5.3.11);
——更改了自用電切換試驗的要求(見6.1.2,2010年版的15.5);
——增加了測量機組噪聲的要求(見6.1.6);
——增加了檢查機組出口開關、滅磁開關聯動和拖動機組出口斷路器在機組低頻時應延時分閘動
作等要求(見6.2.2);
——增加了各工況軸承熱穩定試驗要求(見6.3.5、6.4.3、6.5.2、6.6.4、6.7.5);
——更改了抽水調相工況停機試驗要求(見6.3.7,2010年版的10.7);
——增加了水泵斷電、甩負荷試驗前驗證導葉接力器關閉時間和進行過渡過程計算等要求(見
6.4.3、6.6.3);
——增加了一管雙機切泵試驗(見6.4.3.10);
——增加了檢查各轉速開關量信號動作正常的要求(見6.5.2);
——更改了機組過速試驗的要求(見6.5.3,2010年版的12.5);
——更改了空載工況下轉速擺動相對值的要求(見6.5.4,2010年版的12.3.5);
——更改了發電電動機單相接地保護試驗的要求,增加了注入式定子接地保護試驗(見6.5.7,
2010年版的12.8.3);
——更改了投入勵磁后機端電壓的穩定性和超調量要求(見6.5.8,2010年版的12.9.4);
——更改了帶主變短路升流要求(見6.5.9,2010年版的12.10.1.5);
——增加了發電工況一管雙機甩負荷試驗(見6.6.3.4);
Ⅲ
GB/T18482—2026
——增加了涉網試驗(見6.9);
——刪除了變頻器冷卻系統試驗、變頻器功率部分和控制部分的檢查試驗(見2010年版的
9.1.2.1、9.1.2.2);
——刪除了從零流量工況至抽水工況過渡過程的檢查和試驗(見2010年版的11.2);
——增加了尾水系統充水試驗(見附錄C);
——更改了電站受電的要求(見附錄D,2010年版的第7章);
——將“機組啟動方式選擇”更改為“機組首次啟動方式選擇”,并調整為資料性附錄(見附錄E,
2010年版的第5章);
——更改了機組振動和主軸擺度的要求(見附錄F,2010年版的9.1.3.9)。
本文件由中國電力企業聯合會提出并歸口。
本文件起草單位:國網新源集團有限公司、國網新源控股有限公司抽水蓄能技術經濟研究院、國網
電力工程研究院有限公司、南方電網儲能股份有限公司、國網山東省電力公司電力科學研究院、國網遼
寧省電力有限公司電力科學研究院、國網福建省電力有限公司電力科學研究院、國網冀北電力有限公
司電力科學研究院、水電水利規劃設計總院、中國電建集團華東勘測設計研究院有限公司、東方電氣集
團東方電機有限公司、哈爾濱電機廠有限責任公司、中國水利水電第五工程局有限公司、中國葛洲壩集
團機電建設有限公司、中國水利水電第十四工程局有限公司。
本文件主要起草人:王勝軍、張學清、魏歡、秦俊、蘇勝威、葛軍強、鄧磊、魏春雷、曹坦坦、趙博、田侃、
趙良英、宗萬波、趙常偉、周喜軍、周攀、劉仁、馮雁敏、鄭凱、叢壯、黃琢、關英波、王瑞棟、梁浩、王生瓚、
莫文華、楊慶業、趙志強、李勇、葉飛、陳泓宇、羅胤、陳磊、陳善貴、肖慶華、李成軍、張記坤、尚欣、吳在強、
洪旭剛。
本文件及其所代替文件的歷次版本發布情況為:
——2001年首次發布為GB/T18482—2001,2010年第一次修訂;
——本次為第二次修訂。
Ⅳ
GB/T18482—2026
可逆式抽
溫馨提示
- 1. 本站所提供的標準文本僅供個人學習、研究之用,未經授權,嚴禁復制、發行、匯編、翻譯或網絡傳播等,侵權必究。
- 2. 本站所提供的標準均為PDF格式電子版文本(可閱讀打印),因數字商品的特殊性,一經售出,不提供退換貨服務。
- 3. 標準文檔要求電子版與印刷版保持一致,所以下載的文檔中可能包含空白頁,非文檔質量問題。
最新文檔
- 城市文明指數提升工作總結
- 安全生產機械加工規范講解
- AI配套資源大全
- 景泰藍制胎工測試驗證水平考核試卷含答案
- 園林植保工班組協作強化考核試卷含答案
- 馴馬工安全技能評優考核試卷含答案
- 室內裝飾設計師QC管理能力考核試卷含答案
- 船舶管系工崗中實戰考核試卷含答案
- 乙氧基化裝置操作工安全應急水平考核試卷含答案
- 塑料模壓工安全知識宣貫水平考核試卷含答案
- 2025年醫師定考題庫(附答案)
- 布老虎介紹教學課件
- 2026年時事政治測試題庫100道附完整答案【考點梳理】
- 2026年華為電子 半導體工程師高頻常見面試題包含詳細解答+避坑指南
- 中華人民共和國城市居民委員會組織法(2025修訂)課件
- 土木工程類事業單位考試題庫(附答案+解析)
- 國企事業單位辦公室主任競聘演講資料和筆試題面試題及答案
- DB32-T 5173-2025 建筑施工懸挑式鋼管腳手架安全技術規程
- 《研學旅行課程設計與實施》全套教學課件
- 管材裝車管理辦法
- DBJ51T 189-2022 四川省建設工程施工現場安全資料管理標
評論
0/150
提交評論